Roads

Details of projects under the Greystones Municipal District Roads Programme.

WCCWCCKKi

GREYSTONES WALKING TRAIL 

The Greystones Walking Trail was officially opened by Cllr Derek Mitchell, Cathaoirleach of Greystones Municipal District, on 26th June 2018.

The eight-kilometre trail goes from Greystones train station to Kilmacanogue and connects to the Sugar Loaf Way, via the Burnaby, Kindlestown, Bellvue Hill, Kindlestown Woods, Ballydonagh, the Glenview N11 overbridge and Quill Road.

Access to the walking trail is well served by public transport from Greystones DART, Dublin Bus routes 184, 84, 45a, and Bus Eireann route number 133.

The Wicklow Uplands Council plan to open a walk from Kilmacanogue over the little Sugar Loaf to Bray which will link into the Greystones Way and enable a circular walk of about three to four hours. It is hoped that the new route will eventually connect to the Vartry Reservoir walks at Roundwood and the Wicklow Way.

Greystones Municipal District Councillors allocated their tourism budget for two years to develop this walk.

2024 Road Works 

Department of Transport Tourism and Sport Funded Schemes

Restoration Improvement Schemes - GMD Allocation €984,445

  1. R761 - Kilcoole Road - €190,000 - Proposed
  2. R762 - Church Road, Greystones - €150,000 - Proposed
  3. R762 - Mill Road, Greystones - €25,000 - Proposed
  4. L5050 - Church Road, Newcastle - €220,000 - Proposed
  5. L1027 - Chapel Road - €45,000 - Proposed
  6. L97616 - Crowe Abbey - €80,000 - Proposed
  7. L50552 - Bus Loop, Newcastle - €15,000 - Proposed
  8. L12125-0 - Burnaby Heights - €91,887 - Completed
  9. L12125-1 - Burnaby Heights - €17,244 - Completed
  10. L12125-2 - Burnaby Heights - €9,901 - Completed
  11. L12125-3 - Burnaby Heights - €9,906 - Completed

Restoration Maintenance Schemes

No requirement in GMD for Surface Dressing works in 2024

Climate Adaptation Measures

No allocation to GMD in 2024

Bridge Rehabilitation Works

No allocation to GMD in 2024

Drainage Works - GMD Allocation €48,455

  1. Gulley replacement programme on Victoria Road, Trafalgar Road and Mill Road -  Completed

Safety Improvement Works

1. Delgany Wood Road - formalise roundabouts - €90,000
2. Delgany Wood Road - provide uncontrolled crossing locations - €50,000

National Transport Authority Funded Works

NTA Active Travel Measures

 

Greystones Municipal District Discretionary Funded Schemes

  1. Public lighting at the Pigs Hollow - Fee proposal from Enerveo €25,468.  ESB connections and other items €5,000-€10,000.  Cable trunking installed and lights ordered and awaiting delivery.  ESB connection application submitted.

Footpath Renewal Works - GMD Allocation €100,000

  1. Redford Park, Greystones - Works ongoing
  2. Portland Road, Greystones - Tender awarded
  3. Jack and Jill Hill, Kilcoole - Commenced end of May 2024
  4. Willowbrook Centre Entrance - Tender awarded

Outdoor Recreation Improvement Scheme

2024 allocation to be confirmed

Local Improvement Scheme

2024 allocation to be confirmed

Other Works

  1. St. Crispins Park - as part of the biodiversity plan and anti-dumping initiative circa €7,000 of plants, Berberis and Pyracantha are being planted
  2. Level access provided from south beach car park to the south beach boardwalk at the southern arch

Chapel Road Scheme Update

Work continues, as resources allow, in the preparation of the tender document to allow the Council to tender for construction services.  Some of the next steps, once updated business case is approved, are as follows (dates are preliminary and subject to change):

  • CPO Notice to Treat was served in October 2023
  • Construction tender to be issued ion Q3 2024
  • Contractor to be appointed in Q4 2024